All people, companies and projects shown are synthetic Rillsoft sample data – from the shipped industry packages or, where stated, from a test project.
The prompt
Which suitable candidates are free for the task "Fire walls and partitions"? State availability, free capacity and cost.Read-only mode is enough Licence-dependent function
In your words
- Construction group: Who from the North branch can build the fire walls, and who of them is really free in that period?
- Manufacturing: Which shift leaders fit the pilot series and still have capacity this week?
What you need
- An open project; the task carries at least one role.
- Read-only mode is enough.
- The candidate list is licence-dependent like the role column in the task dialog.
What you get
In the sample package Buildwork Union the answer returns 15 candidates from the two NORTH structural crews for the task Fire walls and partitions of the Eastcamp logistics centre (20 January to 2 February 2027), team filter preset: demand six bricklayers, six already assigned (crew Structural-2), eight with a schedule conflict through the parallel warehouse walls (crew Structural-1), one free. Per candidate: availability, free capacity, cost (40 to 44) and efficiency.
Why it is useful
The answer shows not only who fits but why the fitting ones are not free. Without balance and schedule conflict from the plan an address book shows 15 bricklayers in NORTH – the candidate list shows that one of them is free. That is the moment the planner widens the circle – see the prompt on the preferred team and the example staff across sites.How the answer is produced
The AI requests the candidate list for the task’s UUID; the team filter is preset by the preferred team of the subproject. Demand, balance and conflicts are computed by Rillsoft Project.rillsoft_task_resource_candidate_list
Limits
Schedule conflicts apply within the open project. Machine candidates come from the same prompt with type machine. If the licence function is missing, an error is returned. The Rillsoft Project product page describes the candidate list of the user interface.Try it
Get started- Industry package
09_baukonzern- Product version
- Rillsoft Project 10 (Build 10.0.623)
- Last verified
- 2026-09-27
- Verification
- Figures and statements verified on the named sample package against the named product build – MCP session, view and report; German and English package with identical figures.