Check SAP order capacity with an AI prompt

Validated prompt: read SAP orders via the MCP Gateway, schedule them in Rillsoft Project, report bottlenecks per work centre on the hour scale.

All people, companies and projects shown are synthetic Rillsoft sample data – from the shipped industry packages or, where stated, from a test project.

The prompt

Fetch the orders I name from SAP through the MCP Gateway and fine-plan them in Rillsoft Project. Ask me first: production or maintenance, plant, period (or work centers), grid of the analysis (hour, day or week). Only read in SAP. Show me the mapping SAP → Rillsoft before you create anything. In Rillsoft, work on a copy of the resource pool in a new project and overwrite nothing. Then check: same number of operations and same total time in SAP and Rillsoft. Report load and bottlenecks per work center (machine type or role) in the chosen grid with points in time, and restore Rillsoft to its initial state afterwards. Rescheduling only as a proposal; nothing is changed in SAP. At the end, list which parts you delivered.

Changes the project (one undo step)

Show the detailed prompt
Task: read SAP orders through the MCP Gateway, model them as a project in Rillsoft Project, let Rillsoft calculate the capacity and deliver a report. SAP is read only; in Rillsoft you work on a copy of the pool and restore the initial state at the end. 1. Questions (once, before any call) - Kind: production (production orders with operations) or maintenance (maintenance orders with persons per operation). - Plant, period and optionally work centers or line. Suggest a narrower cut if more than about 300 operations are expected (roughly four Rillsoft calls per operation). - Grid of the analysis: hour, day or week. Bottlenecks within a shift need the hour; on day or week peaks even out. - If the SAP dates lie in the past: shift them by whole weeks? Then keep weekday and time of day and state the shift in every note and in the report. 2. Read SAP (GET tools of the sap-gateway server only; parameters without "$": filter, select, top ≤ 500, skip, orderby) - Production: operations (…ProductionOr_1) with order, operation, text, work center, earliest start and end, standard values 1–3 and their units, quantity; orders (…_A_ProductionOrde) with material and quantity. - Maintenance: operations (…MaintenanceOrderOperat) with order, operation, text, work center, NumberOfCapacities (persons), duration, work, start and end; orders (…_MaintenanceOrder) with text, type, priority, technical object. - Work centers (…A_WorkCenters) and their capacities (…WorkCenterCapacity): capacity category (001 machine, 002 person), number of capacities, shift start/end in seconds, break, factory calendar. - Plant and period in the filter; avoid long OR lists (the iFlow answers HTTP 500), rather read wider and cut yourself. On HTTP 500 retry twice with a pause. - Check the units (minutes or hours) before you calculate. 3. Show the mapping and have it confirmed (create nothing yet) - Order → subproject "Order ‹no› · ‹text or material› · ‹quantity›"; operation → task "‹op no› ‹text› (‹work center›)", note with all SAP values and the original SAP date. - Work center with capacity category 001 → machine type on the task (demand), as many machines of this type in the pool as SAP states capacities (supply). Never attach a concrete machine to overlapping tasks. - Work center with capacity category 002 → role on the task with the number of persons (NumberOfCapacities), as many persons of this role in the pool as SAP states. SAP only delivers the head count: create persons as placeholders ("‹work center› Technician 01") and mark them as Rillsoft data in the report – or use existing persons of the pool if I name them. - Labour time in production (standard value 3) → role from the pool with utilisation = labour time ÷ duration. - Shift → calendar Mon–Fri without a break window. SAP spreads the break evenly: duration = net × shift ÷ (shift − break), in whole minutes. Check the factor against the SAP dates per work center: median of span ÷ duration over the operations within one shift. If it is 1 (SAP plans there without break share), use factor 1 for this work center; state both values in the mapping. - Duration: production = setup + quantity × (machine + labour); maintenance = duration, with duration 0 and work > 0 duration = work ÷ persons (mark it). Duration 0 without work → milestone without machine type/role. - Sequence of operations → finish-to-start dependency only where SAP plans the operations one after another; otherwise starts as in SAP. - State the number of orders, operations, work centers, persons/machines and the expected number of Rillsoft calls. 4. Create in Rillsoft (only after my confirmation) - Save the initial state: rillsoft_resource_pool_get (path, number of persons and roles), rillsoft_project_tree_get. If the open project is not empty or has unsaved changes: ask. - Copy the pool file to a place I name or confirm. rillsoft_project_create without a name (discardChanges: true), rillsoft_resource_pool_file_select on the copy, rillsoft_resource_pool_edit_open, create calendars, teams, roles, machine types, machines, persons, edit_save, edit_close. Take the IDs from the answers (the catalogue shows new entries only after edit_save). - rillsoft_project_update: name with origin (and shift), start/finish, timeStepMinutes 1, durationStepUnit and quantityStepUnit "minute", schedulingMode "deadline_driven", project calendar 7 × 24 h (persons use their own calendar, machines the project calendar – see 6). - Per order rillsoft_subproject_create; per operation rillsoft_task_create (fixedType "duration", note), rillsoft_task_update with the calendarId of the shift, then start and durationHours; machine type via rillsoft_task_machine_role_assignment_set (quantity 1), role via rillsoft_task_role_assignment_set (quantity = persons); dependencies as in 3. - Then per subproject rillsoft_subproject_update with start = earliest operation start and finish = latest operation finish from rillsoft_project_tree_get (like the subproject context command "Take over", which takes the dates from the activities). A new subproject is fixed and otherwise keeps the finish of the project. The operation dates must not change. 5. Reconciliation (before any analysis; if it fails, no report but a message with the figures) - Number of operations SAP = Rillsoft. - Total time: production setup + machine time, maintenance work (duration ÷ factor × persons); deviation at most the minute rounding (½ min × persons per operation). - Start per operation as in SAP (shifted); list deviations individually (e.g. SAP start before the shift). - Start and finish per subproject = earliest start and latest finish of its operations. 6. Let Rillsoft calculate the capacity (Rillsoft calculates, not you) - Save the view first (rillsoft_view_state_get). - Machines: rillsoft_view_state_apply with view {name: "machine_capacity", grouping: ["machine_role"], display: "absolute", capacity: true} and a time filter on the period. Machine supply follows the project calendar: per shift model set the shift calendar as project calendar and read the machine types of this shift from this report. Check that the dates stay the same. - Personnel: view {name: "employee_capacity", grouping: ["role"], display: "absolute", capacity: true}, same time filter. Persons follow their own calendar; one report is enough. - rillsoft_timescale_apply with the chosen grid (for bottlenecks also "hour"), then rillsoft_analysis_report_get. Values are minutes (unit "minute"): divide by 60. Demand = value, supply = sum of offers[].value. - Shortfall = sum of max(0, demand − supply) per time slot, separately for hour, day and week. - Concurrency from the Rillsoft dates: highest number of machines or persons needed at the same time per work center and the periods in which it exceeds the available number. - Afterwards reset the project calendar and the view, do not save. 7. Report (complete) - Header: kind, plant, period, origin of the data (SAP / Rillsoft), shift of the dates, number of calls. - Key findings (three to five, from figures only): largest bottleneck with work center, day and time. - Table per machine type or role: work center, machines/persons from SAP, shift, demand, supply, utilisation, maximum at the same time, shortfall per hour, day and week. - Table of the days or periods with shortfall. State the scale (hour, day or week) with every shortfall; the program's shortfall column calculates to the minute and can exceed the hourly report - say so when you quote it. - Reconciliation with all figures from step 5. - Optional rescheduling: only if I want it, marked as a proposal; Rillsoft has no capacity levelling with rescheduling over MCP – proposal per work center without overlap, never before the SAP start, keep the order sequence, then check in Rillsoft (shortfall 0). Write nothing back to SAP. - Data basis: fields, filters, units, factors, assumptions. 8. Finish - On my request save the project as .rpj next to the pool copy. - rillsoft_project_create without a name, rillsoft_resource_pool_file_select on the original path, check: path, number of persons and roles as before. Same on an abort along the way (edit_close first). - At the end, list which parts were delivered: questions, SAP data, mapping, creation, reconciliation, capacity per report, report with all tables, initial state. What is missing, with the reason.

In your words

  • Production: Fetch the production orders of plant 1710 at the ZAU_ work centres and check machine capacity on the hour scale. The dates are in the past – shift them by whole weeks.
  • Maintenance: Fetch the maintenance orders of plant 1010 with basic start in August and check when the staff per work centre is insufficient, hour scale.
  • Day scale: The same check on the day scale: show me which bottlenecks disappear on day and week and which remain.

What you need

  • Two MCP servers in the AI client: sap-gateway (MCP Gateway of the SAP Integration Suite, read only, via the bridge from the example package) and rillsoft-project (Rillsoft Project 10, build 10.0.626 or newer, write access). Both are free to try: SAP BTP trial and the 30-day trial of Rillsoft Project.
  • Answers to the questions: production or maintenance, plant, period or work centres, grid (hour for bottlenecks within a shift), shift of past dates, location of the pool copy.
  • An empty project without unsaved changes; the AI works on a copy of the resource pool and restores the initial state at the end.
  • Three to five Rillsoft calls per operation: 48 operations need about 300 calls, 117 operations about 600.

What you get

A report with key findings, a table per machine type or role, periods with shortfall, reconciliation and data basis. In the validated run of 24 Oct 2026 (SAP sandbox, build 10.0.626, German and English identical):

Production plant 1710, 48 operations from 6 orders, 367.5 net hours in SAP against 367.48 in Rillsoft, 42 dependencies: battery assembly with one machine is 72 % utilised and still has 21.7 hours of shortfall in 23 hours between 10 and 18 Nov 2026 – SAP double-booked it; on day and week the 21.7 hours remain. The charging station with four chargers needs at most two at once.

Maintenance plant 1010, 117 operations from 30 orders, 173.5 hours of work against 173.8 in Rillsoft: Mechanics RES-0100 with ten persons is only 13 % utilised but requires up to 48 persons on Friday 13 Nov between 10:00 and 12:00 – 24.3 hours of shortfall in two hours, zero on day and week. AMS-200 lacks 37.0 hours in six hours on two days.

Check SAP production order capacity with AI – Rillsoft Project · 1:30 Min Watch on YouTube · Open the playlist The video is loaded from YouTube only after you click. More in the privacy policy.

Why it is useful

SAP’s capacity check ends at the work centre boundary; Rillsoft Project calculates occupancy per machine type and role on a minute grid and shows when the number of machines or persons is insufficient – even when the daily total is fine. The prompt brings both systems together without changing SAP. The results are in the examples production orders and maintenance orders.

How the answer is produced

The AI asks once, reads SAP read-only (plant and period in the filter), shows the mapping – a work centre with machine capacity becomes a machine type with as many machines as SAP names; a work centre with personnel capacity becomes a role with the head count – and creates only after confirmation: pool copy, new project with a 1-minute grid, one subproject per order, one task per operation with shift calendar and occupancy time (break pro rata, factor checked against the SAP dates). Before the report it reconciles the number of operations and the sum of times. Rillsoft calculates the capacity; the AI reads the reports on the hour, day and week scales and states the scale with every shortfall. Connect Rillsoft Project to SAP describes the access, reproduce the demo the step-by-step rebuild.

rillsoft_resource_pool_get rillsoft_project_tree_get rillsoft_project_create rillsoft_resource_pool_file_select rillsoft_resource_pool_edit_open rillsoft_calendar_create rillsoft_resource_pool_resource_create rillsoft_resource_pool_edit_save rillsoft_resource_pool_edit_close rillsoft_resource_pool_catalog_list rillsoft_project_update rillsoft_subproject_create rillsoft_task_create rillsoft_task_update rillsoft_task_machine_role_assignment_set rillsoft_task_role_assignment_set rillsoft_task_dependency_create rillsoft_subproject_update rillsoft_view_state_get rillsoft_view_state_apply rillsoft_timescale_apply rillsoft_analysis_report_get rillsoft_project_file_save_as

Limits

Read-only SAP tools; writing back to SAP is a separate step with approval. The gateway server does not provide the maintenance operation sequence; SAP gives no persons or qualifications, only head counts – persons are placeholders. Rillsoft has no capacity levelling with rescheduling via MCP; date proposals remain proposals. Machine supply follows the project calendar, hence one report per shift model. The program’s shortfall column calculates to the minute and can exceed the hourly report (RES-0100: 31.9 against 24.3 hours). Validated with the SAP sandbox; if its data change, the run reports the deviation. Related pages:

Try it

Get started
Industry package
SAP S/4HANA Cloud sandbox (plants 1710 and 1010) via the example package `integrations/sap` 0.1.0-preview; pool "Machinery and plant engineering"
Product version
Rillsoft Project 10 (Build 10.0.626)
Last verified
2026-10-24
Verification
Figures and statements verified on the named sample package against the named product build – MCP session, view and report; German and English package with identical figures.